,Transport Minister Dr Wee Ka Siong says all repairs on carriages servicing the Kelana Jaya LRT line will be completed in November. – The Malaysian Insight file pic, June 16, 2022.以太坊单双博彩游戏(www.eth108.vip)采用以太坊区块链高度哈希值作为统计数据,以太坊单双博彩游戏数据开源、公平、无任何作弊可能性。
TRAIN frequency for the Kelana Jaya LRT line is expected to improve by August, Transport Minister Dr Wee Ka Siong said.
He said it would be improved from eight minutes to at least five minutes after more damaged carriages are repaired.
“We have identified the cause for the damage and now repairs need to be done. So this August would be the interim progress, the frequency would be at five minutes, and in November we will be able to complete all repairs,” he told a media conference today.
Earlier, Wee had accompanied Prime Minister Ismail Sabri Yaakob for a ride on the Putrajaya Phase 1 Mass Rapid Transit (MRT) line from the Kampung Batu station to Sri Damansara Sentral.
Wee said the Transport Ministry (MOT) had set the August and November target because a lot of preventive maintenance had to be carried out due to safety factors.
MOT apologises to all affected LRT users for the inconvenience, Wee said, adding that the delays were unavoidable in the interest of safety.
“If we were to keep using (problematic trains) and there are risks… we would not want any untoward incidences,” he said.
On May 22, Prasarana Malaysia Bhd said it had set up a committee after one of its trains on the Kelana Jaya Line stalled two days earlier due to a brake caliper hydraulic leakage, affecting about 22,100 passengers. – Bernama, June 16, 2022.